Phase |
Estimated dates |
Budleigh Salterton Cricket club works commence (part of a separate planning application) |
Spring 2021 |
Stage one vegetation clearance |
Jan 2021 – Feb 2021 |
Stage two vegetation clearance and |
May – Jun 2021 |
Construction phase: Tidal creek excavations General earthworks Highway bridge foundation works Footbridge foundation works Big Bank breach works New South Farm Road highway embankment earthworks formed Footpath raising works |
Jul – Oct 2021 |
New South Farm Road highway embankment monitored for settlement over nine month period Footbridge deck installed Highway bridge deck and features installed Small culvert structures installed Service diversions The estuary sewer pipe diversion works may commence early 2022 (separate to this planning application) |
Nov 2021 – Jul 2022 |
New South Farm Road highway embankment completes; surfacing and features installed New highway ties into existing road network Existing Cricket club removal begins |
Aug – Oct 2022 |
Final creeks excavated. Existing South Farm Road surface removed Improvements to existing footpath embankments |
Nov – Dec 2022 |
Little Bank breach works New Budleigh Brook channel connected; existing aqueduct removed Main Southern breach works High tide bird islands formed Landfill area cover finalised Final landscaping features installed |
Jan – Oct 2023 |
Construction phase demobilisation |
Nov 2023 |