Latest updates

Keep up-to-date

Sign-up for project updates

If you’d like to receive emails to let you know about important project updates, please click here.

Contacts

Tell us what you think

To contact the Lower Otter Restoration Project, click here.

Updates Contacts

Q&A

Answers to the most frequently asked questions about the project are available here.

planfaq

Environment

planses

Environmental Statement
To see the Lower Otter Restoration Project Environmental Statement, click here.

Kier Newsletter

Please click here to read the October 2023 Kier Lower Otter Restoration Project newsletter.

Queen’s Green Canopy

The Environment Agency, on behalf of the Lower Otter Restoration Project, has been granted a virtual plaque after planting 225 trees to form part of the Queen’s Green Canopy which marked the 2022 Platinum Jubilee.

Click here to see the plaque.

Work to start on removing section of embankment

25 September, 2023: Following the successful installation of the footbridge, work will now commence on removing a section of the existing tidal embankment adjacent to Lime Kiln Car Park.  

Click here to read more.

Home Email us
PACCo
Your data & privacy Cookies Terms & Conditions Contacts

Website designed and maintained by KOR Communications

© Lower Otter Restoration Project

Lower Otter Restoration Project Search
plans

Planning application - Timetable

Phase

Estimated dates

Budleigh Salterton Cricket club works commence (part of a separate planning application)

Spring 2021


Stage one vegetation clearance

Jan 2021 – Feb 2021

Stage two vegetation clearance and
Construction phase mobilisation  

May – Jun 2021


Construction phase:

Tidal creek excavations

General earthworks

Highway bridge foundation works

Footbridge foundation works

Big Bank breach works

New South Farm Road highway embankment earthworks formed

Footpath raising works

Jul – Oct 2021


New South Farm Road highway embankment monitored for settlement over nine month period

Footbridge deck installed

Highway bridge deck and features installed

Small culvert structures installed

Service diversions

The estuary sewer pipe diversion works may commence early 2022 (separate to this planning application)

Nov 2021 – Jul 2022

New South Farm Road highway embankment completes; surfacing and features installed

New highway ties into existing road network

Existing Cricket club removal begins

Aug – Oct 2022

Final creeks excavated.

Existing South Farm Road surface removed

Improvements to existing footpath embankments

Nov – Dec 2022


Little Bank breach works

New Budleigh Brook channel connected; existing aqueduct removed

Main Southern breach works

High tide bird islands formed

Landfill area cover finalised

Final landscaping features installed


Jan – Oct 2023


Construction phase demobilisation

Nov 2023


Next - Planning application Environmental Statement